Follow along as we build and use our new Family Life Center for God's glory
Christ First - In Heart and Home
Friday, December 29, 2006
Friday, December 15, 2006
Thursday, December 07, 2006
Final, Final Grading
The excavation contractor completes grading and the spreading gravel. The parking lot can now be used for church activities. The last of the structural steel has not yet arrived, but fabrication was done this week. Hopefully it will arrive next week. Window installation will commence either tomorrow or Monday.
Tuesday, November 28, 2006
Final Grading
The excavation contractor is bringing our new parking lot to final grade level and will spread gravel in preparation for paving. The windows are scheduled to arrive next week as are the replacement steel beams for the drive through. The county approval of the building structure is expected this week. Passing this inspection will allow us to proceed to completion.
Tuesday, October 31, 2006
Another Delay On Completing the Drive Through
The structural engineer for our Family Life Center project (Alliance in Richmond) has determined that the steel beams that run between the building and the new steel support columns must meet the original design specifications. This means the re-designed beams that are currently on site must be replaced. This will delay completion of the drive through while new beams are ordered and fabricated. The upside is the drive through will be very strong. The downside is it will take longer to complete.
Sidewalks Poured
Friday, October 13, 2006
Curbs and Gutters Going In
Last of the Steel Arrives
Friday, September 29, 2006
Steel Spaghetti
Work Moves Inside
The exterior brick and the roof are essentially finished with only the drive through remaining. We are awaiting delivery of the additional steel beams needed to replace the masonry columns that have been taken down. Work has moved inside the building with plumbing, electrical and heating/air conditioning contractors hard at work. The grass is starting to come up in the area of the storm drain outlet. This will stabilize the soil to reduce the chance of another washout like we experienced with Tropical Storm Ernesto
Friday, September 15, 2006
First Shiloh Expansion
Roofers Back on the Job
Tuesday, September 12, 2006
Starting Point
Construction Resumes!
Today the county inspected and approved the site work items that caused the hold on construction. This effort took much longer than expected due to damage caused by tropical storm Ernesto. The torrential rainfall washed out part of the storm drain system, repair of which extended the schedule. Work has now resumed on the building.
Thursday, August 31, 2006
Finishing Up Storm Drain System
Friday, August 25, 2006
Site Work Proceeding
DeBernard Construction expects to complete the site work required by the county on Wednesday, August 30th so that work can resume on the new building. Progress has been slower than expected due to an old nemesis - unsuitable soil. A small area of old fill had to be replaced in order to finish the storm drain system. In the photo the new fill is being laid and compacted.
Tuesday, August 15, 2006
Construction Delayed
Work on the Family Life Center has halted until our new excavation contractor completes several site work items required by the county. The new excavator is DeBernard Construction, who is now under contract. DeBenard is expected to start work as early as tomorrow and we expect construction to resume on the building by next week.
Our builder, JH Batten, changed excavation contractors due to performance issues with the original contractor.
Our builder, JH Batten, changed excavation contractors due to performance issues with the original contractor.
Tuesday, August 01, 2006
The Big Picture
Wednesday, July 26, 2006
Almost Ready for Shingles
Most of the roof structure is complete. The masons are making good progress in applying the exterior brick. The roof over the drive-through will be delayed due to a design change, which will add more steel. That steel will not arrive for about a month. This delay will not affect work on the rest of the building. The second photo is taken inside the new fellowship hall from Todd Brinklow's new sound booth. It should put to rest any concerns about whether the new fellowship hall is large enough.
Thursday, July 20, 2006
What a Difference a Week Makes!
The Kitchen/Bathroom area and the Fellowship Hall are under roof. Only the Chapel area remains uncovered. The steel beams that support the cover over the drive through should go up next week allowing the final section of roof to be completed. Notice in the second photo that the masons are back and laying the exterior brick.
Friday, July 14, 2006
Framing Completed
The framing team has completed framing of the exterior and interior walls so the layout of the Family Life Center is now fully apparent. The first photo shows the walls of the chapel with the wrap around handicap ramp. The second photo shows the new kitchen. The third shows the exterior walls, which are ready to receive the roof trusses. The trusses are now scheduled to be set in place starting Monday.
Tuesday, July 11, 2006
Stained Glass Window Update Two
We have received interest from Shiloh members in donating a total of four stained glass windows. The builder is sending information for us to select the final designs and colors. Our intention is to install two of them in the left two openings in the existing wall shown in the photo. The rightmost window will be replaced with a door. The remaining two stained glass windows will be installed in the chapel. The floor of the chapel can be seen in the area surrounded by the handicap ramp and the stairway seen in the photo.
Framing - Finally!
We lost almost two weeks due to weather, holidays and scheduling issues, but the framing crew has started at last. The remaing outside walls of the Family Life Center are of frame construction with brick exterior. They are now starting to go up. The crane is scheduled for Thursday to commence installation of the roof trusses, which have been on-site for some time.
Wednesday, June 21, 2006
Inside the New Family Life Center
Masons Laying Last of the Block
Tuesday, June 13, 2006
Stained Glass Window Update
At the 6 June 2006 Shiloh Business Meeting the church voted to advertise that we were seeking donations to purchase stained glass windows to go where the old nursery windows are now. The stained glass windows would be given as a memorial, just like the existing ones in the sanctuary. The price is approximately $2,500 apiece. The first announcement was made in last Sunday's bulletin and two families responded with interest in donating windows. So it appears that we will be getting these windows. If additional families are interested, it would be possible to put two more stained glass windows in the chapel.
Steel Going Up
Friday, June 02, 2006
Wednesday, May 31, 2006
Progress Restarted
Thursday, May 11, 2006
View Through the Foyer Window
The interior of the Fellowship Hall takes shape as the block walls go up.
Stained glass windows anyone? The architect has suggested that instead of bricking up the two windows (seen at the left side of the existing building) that we instead install stained glass windows. The stained glass windows would be lighted from behind. This existing exterior wall becomes an interior exposed-brick firewall in the new building. We have asked the builder to quote us a price, which will be posted when available. We will then offer families the opportunity to donate one or both windows. Here is a way to create a beautiful memorial to a loved one, just like the existing stained glass windows in the sanctuary.
Thursday, May 04, 2006
Wednesday, April 26, 2006
Masons Back on the Job
Slab Poured
Tuesday, April 18, 2006
Rain Delays Pour of Slab
The under-slab plumbing and electrical work is complete and has passed county inspection. The amount of rain we received in recent days will require us to wait a bit before we pour the slab. This will give the soil time to dry out so the moisture won't be trapped under the concrete floor of the new building.
Wednesday, April 12, 2006
Don't Forget the Memory Bricks
Mike Rose holds up the Memory Brick purchased in honor of Mary Burnley Owens. Memory Bricks will be set in the walkway to the new building, creating a lasting memorial to those whose names are inscribed on them. All brick proceeds go towards the new building construction cost. If there is enough interest, we may establish a series of memory bricks using the recently discovered bricks from the original Shiloh Church building. Please see Mike if you wish to purchase a brick.
Tuesday, April 11, 2006
New Bathrooms Almost Ready
Well - The drains for the new bathrooms are ready. The next step is to fill the inside of the foundation with gravel and rebar in preparation for pouring the slab. That pour is scheduled for next week. The gravel mountain shown below will be partially used for the under-slab gravel. The remainder will be used to surface a temporary parking area where the new parking lot will be located.
Thursday, April 06, 2006
Old and New
No it is not Jim Rodante who is old, but the brick he is holding. Jim is the JH Batten site superintendent. He discovered a cache of bricks during excavation of the footings for the new building. These bricks are old and of a size that pre-date the current buildings at Shiloh. More of them can be seen at his left. It is believed these bricks are from the original church that was destroyed in the tornado in 1948. Jim placed one of them in the concrete as it was being poured for the Family Life Center foundation - thus ensuring that a bit of the oldest building is part of the newest one.
Plumbers Lay Building Drains
Friday, March 31, 2006
Masons Finish Foundation
Subscribe to:
Posts (Atom)