Friday, September 29, 2006
Work Moves Inside
The exterior brick and the roof are essentially finished with only the drive through remaining. We are awaiting delivery of the additional steel beams needed to replace the masonry columns that have been taken down. Work has moved inside the building with plumbing, electrical and heating/air conditioning contractors hard at work. The grass is starting to come up in the area of the storm drain outlet. This will stabilize the soil to reduce the chance of another washout like we experienced with Tropical Storm Ernesto