Follow along as we build and use our new Family Life Center for God's glory
Christ First - In Heart and Home
Wednesday, February 07, 2007
Church Votes to Approve Cost Increase
At the 6 February Shiloh business meeting the church voted to authorize the New Building Committee to pay the additional costs of constructing the Family Life Center. A budget for tables and chairs was also approved. The builder is currently projecting completion during the first week in April.
Wednesday, January 31, 2007
Remembering our Service Members

Shiloh has several members serving with the armed forces overseas. We are greatly appreciative of their sacrifice and pray for their safe return. One of them is monitoring our construction progress via this blog. Here is a view of the new Family Life Center taken from Route 3 and with a few liberties with the J H Batten construction sign.
Rapid Progress

The framing on the drive through is almost complete. Once finished, the masons will begin to lay the brick that covers the framing. One of the steel lintels that support the brick over the archway can be seen in the foreground. Nearly all windows and doors are installed. The exceptions are the stained glass that will go in the round openings and the front glass doors that were damaged in shipment and are being replaced.
Inside, most of the sheetrock is installed and the heating and air conditioning ductwork is going in. Electrical and phone wiring is complete.

Wednesday, January 03, 2007
Friday, December 29, 2006
Friday, December 15, 2006
Thursday, December 07, 2006
Final, Final Grading

The excavation contractor completes grading and the spreading gravel. The parking lot can now be used for church activities. The last of the structural steel has not yet arrived, but fabrication was

Tuesday, November 28, 2006
Final Grading

The excavation contractor is bringing our new parking lot to final grade level and will spread gravel in preparation for paving. The windows are scheduled to arrive next week as are the replacement steel beams for the drive through. The county

Tuesday, October 31, 2006
Another Delay On Completing the Drive Through
The structural engineer for our Family Life Center project (Alliance in Richmond) has determined that the steel beams that run between the building and the new steel support columns must meet the original design specifications. This means the re-designed beams that are currently on site must be replaced. This will delay completion of the drive through while new beams are ordered and fabricated. The upside is the drive through will be very strong. The downside is it will take longer to complete.
Sidewalks Poured
Friday, October 13, 2006
Curbs and Gutters Going In
Last of the Steel Arrives
Friday, September 29, 2006
Steel Spaghetti
Work Moves Inside

The exterior brick and the roof are essentially finished with only the drive through remaining. We are awaiting delivery of the additional steel beams needed to replace the masonry columns that have been taken down. Work has moved inside the

Friday, September 15, 2006
First Shiloh Expansion
Roofers Back on the Job
Tuesday, September 12, 2006
Starting Point
Construction Resumes!
Today the county inspected and approved the site work items that caused the hold on construction. This effort took much longer than expected due to damage caused by tropical storm Ernesto. The torrential rainfall washed out part of the storm drain system, repair of which extended the schedule. Work has now resumed on the building.
Thursday, August 31, 2006
Finishing Up Storm Drain System
Friday, August 25, 2006
Site Work Proceeding

DeBernard Construction expects to complete the site work required by the county on Wednesday, August 30th so that work can resume on the new building. Progress has been slower than expected due to an old nemesis - unsuitable soil. A small area of old fill had to be replaced in order to finish the storm drain system. In the photo the new fill is being laid and compacted.
Subscribe to:
Posts (Atom)