Sunday, March 19, 2006

At Last!


Digging of the footings has started! The block has been delivered and concrete is planned to arrive this Monday (3/20/06). This week will mark the transition from site preparation to actual construction.
Posted by Luke Miller at 11:10 AM
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest

No comments:

Post a Comment

Newer Post Older Post Home
Subscribe to: Post Comments (Atom)

Contributors

  • Chalkley
  • Luke Miller

Blog Archive

  • ►  2007 (18)
    • ►  June (3)
    • ►  May (1)
    • ►  April (1)
    • ►  March (9)
    • ►  February (1)
    • ►  January (3)
  • ▼  2006 (58)
    • ►  December (3)
    • ►  November (1)
    • ►  October (4)
    • ►  September (6)
    • ►  August (4)
    • ►  July (5)
    • ►  June (5)
    • ►  May (3)
    • ►  April (7)
    • ▼  March (10)
      • Masons Finish Foundation
      • Unsuitable Soil Problem Costly
      • Tree Spared!
      • Block Work Continues
      • Masons Have Started Work
      • Ready for Final Pour
      • Foundation Started
      • At Last!
      • Ready to Dig Footings
      • Building Permit Issued!
    • ►  February (7)
    • ►  January (3)
  • ►  2005 (2)
    • ►  November (2)
Simple theme. Powered by Blogger.