Building Permit Issued!

We now have our building permit and the site grading is complete. The storm drain culvert for the new parking lot is being installed today. The concrete contractor has commenced mobilization to our site and will pour the footings as soon as they are excavated. That excavation work should commence tomorrow. We expect the mason to begin laying block on the footings next week. We plan to meet with VDOT in two weeks to address the modifications to the left turn lane needed to spare our oak tree.